Replacement windows and doors (occupied home): answer the questions and preview a RAMS written for that job, free. Download it as an editable Word file for £9.99.

Build your RAMS online →

Rather not write it yourself? We'll write your RAMS for the job for £79, or check and fix the one you've got for £49. Back to you within 2 working days. See the RAMS services →

Typical jobs in a RAMS for window fitters

A RAMS (risk assessment and method statement) should describe the actual job, not the trade in general. These are the jobs window fitters are most often asked to write one for:

Main hazards and control measures for window fitters

These are the hazards that usually belong in the risk assessment, with the kind of controls a site manager expects to see. Adjust them for your job; every site is different.

HazardTypical control measures
Handling heavy glazed unitsTwo-person lifts, glass suckers or carrying frames, and lifting aids for large units.
Falls when working at upper floorsFit from inside where possible, use towers or platforms outside, and never lean out of open openings.
Cuts from broken glassGloves and arm protection, remove old glass carefully and bag broken glass.
Falling frames and glass onto people belowExclusion zones below, remove old frames inwards where possible.
Expanding foam and sealantsCOSHH assessments from the safety data sheets (some foams contain isocyanates), ventilation and gloves.
Asbestos in older window boards and panelsCheck the asbestos survey before removing old panels or boards in older buildings.

What a main contractor usually expects to see

Formats vary, but when a site manager reads a RAMS from window fitters, they usually look for:

Generic, copy-and-paste RAMS are the ones that get sent back. See the RAMS mistakes that get documents rejected.

Worked example: one method statement step

A method statement sets out the job in the order it happens. Here’s an illustrative extract for one step. Yours should match your own job and site.

Method statement extract · Window Fitters

Step 2: Removing the old window

  1. Clear and protect the room inside, and set up an exclusion zone outside below the opening.
  2. Check the asbestos survey covers any old boards or panels.
  3. Take out the glass first, working from inside, and bag it straight away.
  4. Cut and remove the frame inwards. Don't lean out of the opening.
  5. Make the opening secure if the new frame can't be fitted the same day.

Each step is short and specific, and names the control at the point it’s needed. New to method statements? Read what is a method statement?

RAMS FAQs for window fitters

Do window fitters need a RAMS?

Housing providers and commercial clients usually ask for one. You must always assess and manage the risks, and businesses with five or more employees must record the main findings.

Is it safer to fit upper-floor windows from inside?

Often, yes, but it depends on the size and weight of the unit. Say in the RAMS how you'll do it and why. See HSE's work at height guidance.

What should a window RAMS say about expanding foam?

Name the product, its main hazards from the safety data sheet, ventilation, gloves and how you'll store it. See HSE's COSHH guidance.

Get your RAMS sorted. Our Window Fitters Health & Safety Pack (£9.99, editable Word) includes a health and safety policy, five risk assessments and a method statement written for window fitters, ready to edit for your job. Short of time? We’ll write your RAMS for you (£79, back within 2 working days), or review and fix the one you’ve already got (£49). Prefer to answer a few questions? Build your RAMS online: free preview, £9.99 for the editable Word file.

Useful HSE guidance: HSE: work at height · HSE: manual handling · HSE: asbestos.

This is general guidance, not legal advice. Check the current HSE guidance and what your client asks for.

Continue readingRAMS for other trades→Risk assessment and method statement: what’s the difference?