What is a method statement?
A method statement sets out, in the order the work will happen, how you will do the job and keep people safe while you do it. A risk assessment spots the hazards; the method statement says what you will actually do about them, from setting up to clearing away.
When a site asks for “RAMS”, that is the risk assessment and method statement together. We explain how they fit together in risk assessment and method statement: what’s the difference?
What goes in a method statement?
Formats vary from site to site, but most method statements cover:
- The job: what the work is, where it is and when it will happen
- Who is doing it, and who is in charge on the day
- Tools, equipment and materials, including anything hazardous
- Access, set-up and protecting other people (the public, residents, other trades)
- The sequence of work, step by step
- The main hazards and the controls for each, matching your risk assessment
- PPE and any training or competence needed
- Emergency arrangements: first aid, fire, who to call
- Waste, clearing up and handing the area back
- A sign-off sheet so everyone doing the work has read it
A short example of the sequence
Say you are repainting a stairwell in an office that stays open. The sequence might run:
- Agree working hours, access and restricted areas with the site contact.
- Put up signs, set out the work area and protect surfaces and furniture.
- Prepare the surfaces, noting any dust and how you will control it.
- Apply the paint, with ventilation and the product’s safety information to hand.
- Clear away waste, remove signs and hand the area back.
Each step is short and specific. That is what a site manager is looking for.
Who asks for a method statement?
Principal contractors, facilities managers and clients on commercial, healthcare, school and larger sites are the usual ones. Domestic customers rarely ask. If you are not sure, ask what format they want and when they need it, ideally before the morning you are due to start.

Ranger’s tipWrite the steps in the order you will actually do them on the day. If a new starter could follow it, it is probably clear enough.
Method statement FAQs
Is a method statement a legal requirement?
There is no single legal form called a method statement that every job needs. The law is about managing the risks of your work, and on construction projects the CDM 2015 rules apply (see the HSE construction guidance). In practice, many clients make a method statement a condition of getting on site. Check the current HSE guidance and what your client asks for.
How long should a method statement be?
As long as it needs to be for the person doing the work to follow it, and no longer. For a small job that is often a page or two. Short and specific beats long and generic.
Can I reuse a method statement?
You can use an old one as a starting point, but change it for each job. Different access, neighbours or ground conditions mean different hazards, and a copy-and-paste version tends to get sent back.
What is the difference between a method statement and RAMS?
RAMS means risk assessment and method statement. The method statement is one half of it.
For more on how HSE expects risks to be managed, see the HSE guide to managing risks.