The short answer
- Risk assessment: what could cause harm, who could be harmed, and what you will do to reduce the risk.
- Method statement: how the work will be carried out, in order, so the controls actually happen.
- RAMS: the two combined, usually as one document for one job.
What does a risk assessment cover?
HSE describes risk assessment as a simple process: identify the hazards, assess the risks, control them, record your findings and review the controls. You think about who might be harmed and how, what you are already doing, and what more is needed. See the HSE steps for managing risk.
A risk assessment answers “what are the dangers here, and are they under control?” It is about the hazards, not the order of the work.
What does a method statement cover?
The method statement answers “how are we going to do this?” It lists the steps in sequence, the people, equipment and materials, access, emergency arrangements and sign-off. We cover it in more detail in what is a method statement?
How they fit together
The two documents should agree with each other. If your risk assessment says dust will be controlled with extraction, the method statement should say when and how that happens in the sequence. If a step in the method statement creates a hazard the risk assessment missed, one of them needs updating.
| Risk assessment | Method statement | |
|---|---|---|
| Main question | What could go wrong? | How will we do it safely? |
| Organised by | Hazard | Order of work |
| Used by | You and your client | The people doing the job |
Example: the same job, both documents
Take replacing a section of guttering from a tower scaffold. The risk assessment picks out the hazards: working at height, falling tools, other people walking below, and the weather. It records the controls, such as edge protection, an exclusion zone and a decision not to work in high winds.
The method statement then puts those controls into the order of work: check the scaffold, set up the exclusion zone, lift materials with a rope or hoist, fix the new section, clear away and take down the barriers. Anyone reading both should see the same job described twice, once by hazard and once by step.

Ranger’s tipNot sure what a site wants? Ask whether they expect one combined RAMS or the two documents separately before you start writing.
Risk assessment and method statement FAQs
Do I need both?
It depends on the job and who is asking. A smaller domestic job may only need a basic risk assessment. Principal contractors on commercial and larger sites usually want both, so ask what they require before you start.
Do they have to be one document?
No. Some sites accept two documents; others want a single RAMS. Follow the format your client asks for.
Is a RAMS the same as a risk assessment?
Not quite. A risk assessment is one half of a RAMS. A RAMS also includes the method statement.
Who should write them?
Whoever understands the job and the site, so usually the person doing or running the work. You can use templates to save time, but they need to describe your actual job. Check the current HSE guidance on competence and on recording risk assessments.