Typical jobs in a RAMS for landscapers

A RAMS (risk assessment and method statement) should describe the actual job, not the trade in general. These are the jobs landscapers are most often asked to write one for:

Main hazards and control measures for landscapers

These are the hazards that usually belong in the risk assessment, with the kind of controls a site manager expects to see. Adjust them for your job; every site is different.

HazardTypical control measures
Striking buried services when diggingCheck service drawings, scan with a cable avoidance tool before and during digging, hand-dig trial holes near services, and follow HSG47.
Plant such as mini-diggers and dumpersTrained operators, pre-use checks, seatbelts worn, exclusion zones and a banksman when reversing or near people.
Silica dust when cutting paving and kerbsCut-off saws with water suppression or extraction, suitable RPE, and cut away from others.
Hand-arm vibration from breakers, compactors and sawsLow-vibration tools, limit trigger time and keep a record of exposure.
Manual handling of slabs, kerbs and sleepersVacuum lifters or kerb grabs, team lifts, and deliveries close to the work.
Noise, weather and the publicHearing protection, sun and cold protection, and fencing off the work from the public.

What a main contractor usually expects to see

Formats vary, but when a site manager reads a RAMS from landscapers, they usually look for:

Generic, copy-and-paste RAMS are the ones that get sent back. See the RAMS mistakes that get documents rejected.

Worked example: one method statement step

A method statement sets out the job in the order it happens. Here’s an illustrative extract for one step. Yours should match your own job and site.

Method statement extract · Landscapers

Step 2: Excavating for the patio base

  1. Check the service drawings and scan the area with a cable avoidance tool and signal generator. Mark any services found.
  2. Hand-dig trial holes to confirm the position of any services near the dig.
  3. Fence off the working area and agree the banksman's signals with the digger operator.
  4. Excavate to the planned depth, re-scanning as you go. Hand-dig near marked services.
  5. Stop work and report any unexpected service or object.

Each step is short and specific, and names the control at the point it’s needed. New to method statements? Read what is a method statement?

RAMS FAQs for landscapers

Do landscapers need a RAMS?

On commercial and public jobs, the client will usually ask. You must assess and manage the risks either way, and businesses with five or more employees must record the main findings.

What does HSG47 cover?

HSG47 is HSE's guidance on avoiding danger from underground services. It covers planning, locating services and safe digging. See HSG47 on the HSE website.

Do I need to record vibration exposure?

Where your team uses vibrating tools regularly, you need to assess and control the exposure. See HSE's vibration guidance.

Get your RAMS sorted. Our Landscapers Health & Safety Pack (£9.99, editable Word) includes a health and safety policy, five risk assessments and a method statement written for landscapers, ready to edit for your job. Short of time? We’ll write your RAMS for you (£79, back within 2 working days), or review and fix the one you’ve already got (£49). Prefer to answer a few questions? Build your RAMS online: free preview, £9.99 for the editable Word file.

Useful HSE guidance: HSE HSG47: avoiding underground services · HSE: vibration · HSE: COSHH.