Typical jobs in a RAMS for groundworkers
A RAMS (risk assessment and method statement) should describe the actual job, not the trade in general. These are the jobs groundworkers are most often asked to write one for:
- Foundation and footing excavation
- Drainage and service trenches
- Kerbs, edgings and hard landscaping bases
- Concrete pours and slabs
- Muck-away and backfilling
Main hazards and control measures for groundworkers
These are the hazards that usually belong in the risk assessment, with the kind of controls a site manager expects to see. Adjust them for your job; every site is different.
| Hazard | Typical control measures |
|---|---|
| Striking buried services (electric, gas, water) | Service drawings obtained, CAT and Genny scan before and during digging, trial holes by hand near services, and a permit to dig where the client uses one. |
| Trench or excavation collapse | Battering back or trench support chosen for the ground and depth, daily inspection of the excavation, and no entry until it is checked. |
| People and vehicles falling into the excavation | Edge protection or barriers, spoil and materials kept back from the edge, and stop blocks for tipping vehicles. |
| Being struck by plant | Trained and competent operators, exclusion zones, a banksman where visibility is limited, and segregated walkways. |
| Silica dust from cutting kerbs, slabs and concrete | Wet cutting or on-tool extraction, suitable RPE, and cutting downwind of others. |
| Cement and concrete burns | Gloves and long sleeves, washing facilities on site, and a COSHH assessment for cement products. |
What a main contractor usually expects to see
Formats vary, but when a site manager reads a RAMS from groundworkers, they usually look for:
- How services will be located and who has the drawings
- Excavation support and inspection arrangements
- Plant operator competence and exclusion zones
- Edge protection around open excavations
- COSHH assessments for cement, concrete and fuel
- An operative sign-off sheet
- Site-specific details: address, dates, access route, welfare and emergency arrangements
Generic, copy-and-paste RAMS are the ones that get sent back. See the RAMS mistakes that get documents rejected.
Worked example: one method statement step
A method statement sets out the job in the order it happens. Here’s an illustrative extract for one step. Yours should match your own job and site.
Step 2: Excavating the trench
- Confirm the area has been scanned and marked, and check the drawings against the marks.
- Hand dig trial holes where services are shown or suspected.
- Excavate with the agreed support method, keeping spoil at least the agreed distance from the edge.
- Put barriers around the open trench before leaving it.
- Inspect the excavation before anyone enters, and at the start of each shift.
Each step is short and specific, and names the control at the point it’s needed. New to method statements? Read what is a method statement? Need COSHH assessments too? See what is a COSHH assessment?
RAMS FAQs for groundworkers
Do groundworkers need a RAMS?
Main contractors and commercial clients usually ask for one before excavation starts. You must always assess and manage the risks, and businesses with five or more employees must record the main findings.
What should an excavation method statement include?
The sequence of the dig, how services will be located, how the sides will be supported, how plant and people are kept apart, and how the excavation is inspected and protected.
Do I need COSHH assessments for cement and concrete?
Yes for hazardous products. Use each product's safety data sheet. See HSE's COSHH guidance.
Get your RAMS sorted. Short of time? We’ll write your RAMS for you (£79, back within 2 working days), or review and fix the one you’ve already got (£49). For the supporting assessments, our Noise & Vibration Assessment Pack and Manual Handling Assessment Pack are £9.99 each as editable Word files. Or build your RAMS online: free preview, £9.99 for the editable Word file.
Useful HSE guidance: HSE: construction · HSE: COSHH.
This is general guidance, not legal advice. Check the current HSE guidance and what your client asks for.