Typical jobs in a RAMS for demolition and strip-out

A RAMS (risk assessment and method statement) should describe the actual job, not the trade in general. These are the jobs demolition and strip-out are most often asked to write one for:

Main hazards and control measures for demolition and strip-out

These are the hazards that usually belong in the risk assessment, with the kind of controls a site manager expects to see. Adjust them for your job; every site is different.

HazardTypical control measures
Disturbing asbestosA refurbishment and demolition asbestos survey checked before work starts, stop-work procedure if suspect material is found, and asbestos awareness for the team.
Live servicesElectric, gas and water isolated and confirmed by a competent person before strip-out, and redundant services clearly marked.
Unplanned collapseStructural elements identified before removal, temporary support where needed, and work in the agreed sequence.
Dust (including silica)On-tool extraction, damping down, suitable RPE and sheeting off the work area.
Noise and vibration from breakersLow-vibration tools, rotating tasks, exposure kept within limits and hearing protection.
Falling materials and debrisExclusion zones, debris chutes or controlled lowering, and keeping walkways clear.

What a main contractor usually expects to see

Formats vary, but when a site manager reads a RAMS from demolition and strip-out, they usually look for:

Generic, copy-and-paste RAMS are the ones that get sent back. See the RAMS mistakes that get documents rejected.

Worked example: one method statement step

A method statement sets out the job in the order it happens. Here’s an illustrative extract for one step. Yours should match your own job and site.

Method statement extract · Demolition & Strip-Out

Step 1: Preparing the area for strip-out

  1. Check the asbestos survey covers the areas to be stripped, and brief the team on its findings.
  2. Confirm services are isolated and marked as safe by a competent person.
  3. Sheet off and protect areas not being worked on.
  4. Set up extraction and the waste route before removal starts.
  5. Stop work and report if any suspect material is found that is not on the survey.

Each step is short and specific, and names the control at the point it’s needed. New to method statements? Read what is a method statement? Need COSHH assessments too? See what is a COSHH assessment?

RAMS FAQs for demolition and strip-out

Do I need a RAMS for a soft strip?

Main contractors and commercial clients usually ask for one. You must always assess and manage the risks, and businesses with five or more employees must record the main findings.

Do I need an asbestos survey before strip-out?

For refurbishment or demolition of buildings built before 2000, the client or duty holder should arrange a refurbishment and demolition survey. See HSE's asbestos guidance.

What waste paperwork do I need?

Use a registered waste carrier and keep waste transfer notes. Check the Environment Agency guidance for your area.

Get your RAMS sorted. Short of time? We’ll write your RAMS for you (£79, back within 2 working days), or review and fix the one you’ve already got (£49). For the supporting assessments, our Asbestos Awareness Pack and Environmental & Waste Management Pack are £9.99 each as editable Word files. Or build your RAMS online: free preview, £9.99 for the editable Word file.

Useful HSE guidance: HSE: asbestos · HSE: construction.

This is general guidance, not legal advice. Check the current HSE guidance and what your client asks for.