Typical jobs in a RAMS for carpenters and joiners
A RAMS (risk assessment and method statement) should describe the actual job, not the trade in general. These are the jobs carpenters and joiners are most often asked to write one for:
- First fix: floor joists, stud walls and roof structures
- Second fix: doors, skirting, architrave and staircases
- Kitchen and fitted furniture installs
- Timber frame and roof truss installs
- Shopfitting and commercial fit-out joinery
Main hazards and control measures for carpenters and joiners
These are the hazards that usually belong in the risk assessment, with the kind of controls a site manager expects to see. Adjust them for your job; every site is different.
| Hazard | Typical control measures |
|---|---|
| Cuts and amputations from saws | Guards in place, the right blade, push sticks, and saws only used by trained people. |
| Wood and MDF dust | On-tool extraction (such as an M-class extractor), suitable RPE and cleaning by vacuum, not brushing. |
| Falls through open joists and from roof structures | Boarded or netted floors, edge protection, and working from platforms rather than standing on joists. |
| Nail guns | Trained users only, sequential trigger mode, and never pointed at anyone. |
| Manual handling sheet materials, doors and timber | Team lifts, board lifters and planned deliveries close to the work. |
| Noise | Hearing protection when cutting, and quieter tools where possible. |
What a main contractor usually expects to see
Formats vary, but when a site manager reads a RAMS from carpenters and joiners, they usually look for:
- Cards and training for your team, including any for powered access
- Tool checks and guards (many sites require 110V or battery tools)
- Dust extraction and RPE
- How falls through open floors and roofs are prevented
- COSHH assessments for timber treatments and adhesives
- Waste removal and housekeeping
- Site-specific details: address, dates, access route, welfare and emergency arrangements
Generic, copy-and-paste RAMS are the ones that get sent back. See the RAMS mistakes that get documents rejected.
Worked example: one method statement step
A method statement sets out the job in the order it happens. Here’s an illustrative extract for one step. Yours should match your own job and site.
Step 4: Fixing floor joists at first floor
- Confirm the scaffold edge protection is in place around the first floor.
- Fit joists working from the scaffold or a boarded working platform, not from the joists themselves.
- Board or net each area as joists are completed.
- Cut timber at a set-up cutting station with extraction and hearing protection.
- Keep offcuts cleared so the deck stays free of trip hazards.
Each step is short and specific, and names the control at the point it’s needed. New to method statements? Read what is a method statement?
RAMS FAQs for carpenters and joiners
Do carpenters need a RAMS?
Most commercial and new-build sites ask for one before you start. You must always assess and manage the risks, and businesses with five or more employees must record the main findings.
Is wood dust a COSHH hazard?
Yes. HSE says wood dust can cause asthma, and hardwood dust can cause cancer, particularly of the nose. See HSE's wood dust guidance.
What's the most common gap in a carpentry RAMS?
Not saying how falls through open joists or roof structures will be prevented. Say exactly what you'll stand on and when floors will be boarded.
Get your RAMS sorted. Our Carpenters & Joiners Health & Safety Pack (£9.99, editable Word) includes a health and safety policy, five risk assessments and a method statement written for carpenters and joiners, ready to edit for your job. Short of time? We’ll write your RAMS for you (£79, back within 2 working days), or review and fix the one you’ve already got (£49). Prefer to answer a few questions? Build your RAMS online: free preview, £9.99 for the editable Word file.
Useful HSE guidance: HSE: woodworking · HSE: work at height · HSE: noise.
This is general guidance, not legal advice. Check the current HSE guidance and what your client asks for.