Typical jobs in a RAMS for bricklayers

A RAMS (risk assessment and method statement) should describe the actual job, not the trade in general. These are the jobs bricklayers are most often asked to write one for:

Main hazards and control measures for bricklayers

These are the hazards that usually belong in the risk assessment, with the kind of controls a site manager expects to see. Adjust them for your job; every site is different.

HazardTypical control measures
Falls from scaffold and working platformsWork only from inspected scaffold with guard rails and toe boards. Only scaffolders alter the scaffold.
Manual handling heavy blocks and bricksChoose lighter blocks where possible, use mechanical aids and team lifts, and keep loads at waist height on the scaffold.
Wet cement and mortar burns and dermatitisGloves and long sleeves, wash skin promptly, and have washing facilities on site.
Silica dust when cutting bricks and blocksSaws with water suppression or extraction, suitable RPE, and cut away from others.
Falling bricks and materialsBrick guards, no overloading the scaffold, and exclusion zones below.
Mixers and toolsPre-use checks, guards in place, 110V or battery tools on site.

What a main contractor usually expects to see

Formats vary, but when a site manager reads a RAMS from bricklayers, they usually look for:

Generic, copy-and-paste RAMS are the ones that get sent back. See the RAMS mistakes that get documents rejected.

Worked example: one method statement step

A method statement sets out the job in the order it happens. Here’s an illustrative extract for one step. Yours should match your own job and site.

Method statement extract · Bricklayers

Step 3: Laying blockwork from the scaffold

  1. Check the scaffold tag is current and the guard rails and brick guards are in place.
  2. Load out blocks and mortar boards within the scaffold's loading limits, spreading the load.
  3. Lay blocks from waist height where possible, with two-person lifts for heavier blocks.
  4. Cut blocks at ground level using a saw with water suppression, wearing RPE.
  5. Keep the platform clear of offcuts and wash down tools at the end of the day.

Each step is short and specific, and names the control at the point it’s needed. New to method statements? Read what is a method statement?

RAMS FAQs for bricklayers

Do bricklayers need a RAMS?

Most housing developers and main contractors ask for one before you start. You must always assess and manage the risks, and businesses with five or more employees must record the main findings.

Can bricklayers adjust the scaffold?

No, only competent scaffolders should alter a scaffold. If a lift needs raising or a board moving, ask the site to arrange it.

What should a brickwork RAMS say about dust?

Say which materials you'll cut, how (water suppression or extraction) and what RPE you'll use. See HSE's construction health risks guidance.

Get your RAMS sorted. Our Bricklayers Health & Safety Pack (£9.99, editable Word) includes a health and safety policy, five risk assessments and a method statement written for bricklayers, ready to edit for your job. Short of time? We’ll write your RAMS for you (£79, back within 2 working days), or review and fix the one you’ve already got (£49). Prefer to answer a few questions? Build your RAMS online: free preview, £9.99 for the editable Word file.

Useful HSE guidance: HSE: construction health risks · HSE: work at height · HSE: manual handling.

This is general guidance, not legal advice. Check the current HSE guidance and what your client asks for.

Continue readingRAMS for other trades→Risk assessment and method statement: what’s the difference?