Typical jobs in a RAMS for air conditioning installers

A RAMS (risk assessment and method statement) should describe the actual job, not the trade in general. These are the jobs air conditioning installers are most often asked to write one for:

Main hazards and control measures for air conditioning installers

These are the hazards that usually belong in the risk assessment, with the kind of controls a site manager expects to see. Adjust them for your job; every site is different.

HazardTypical control measures
Working at height on ladders, towers or roofsRight access equipment for the task, towers built by trained people, and edge protection or a MEWP for roof work.
Lifting and fixing outdoor unitsTeam lifts or lifting aids, brackets suitable for the wall, and an exclusion zone below.
Refrigerant handlingF-gas certified operatives, leak checks, ventilation, and gloves and eye protection when connecting.
Brazing and hot worksHot works permit where required, fire extinguisher at hand, heat mat, and a fire check after finishing.
Electrical connectionSafe isolation and lock-off before connecting, and work done by a competent electrician.
Dust from core drillingWater-fed or extracted coring, suitable RPE, and checking for hidden cables and pipes first.

What a main contractor usually expects to see

Formats vary, but when a site manager reads a RAMS from air conditioning installers, they usually look for:

Generic, copy-and-paste RAMS are the ones that get sent back. See the RAMS mistakes that get documents rejected.

Worked example: one method statement step

A method statement sets out the job in the order it happens. Here’s an illustrative extract for one step. Yours should match your own job and site.

Method statement extract · Air Conditioning Installers

Step 4: Brazing the pipework

  1. Check if the site requires a hot works permit and get it before starting.
  2. Clear combustibles from the area and put a heat mat behind the joint.
  3. Purge the pipework with nitrogen while brazing.
  4. Keep a suitable extinguisher at hand.
  5. Check the area for smouldering at the end of the work and again before leaving.

Each step is short and specific, and names the control at the point it’s needed. New to method statements? Read what is a method statement? Need COSHH assessments too? See what is a COSHH assessment?

RAMS FAQs for air conditioning installers

Do AC installers need a RAMS?

Main contractors and commercial clients usually ask for one. You must always assess and manage the risks, and businesses with five or more employees must record the main findings.

Do I need F-gas certification?

Work on systems containing fluorinated gases must be done by people holding the right F-gas certificate. Check the current government guidance.

Is brazing hot work?

Yes. Many sites run a hot works permit system, so ask the main contractor before you start.

Get your RAMS sorted. Short of time? We’ll write your RAMS for you (£79, back within 2 working days), or review and fix the one you’ve already got (£49). For the supporting assessments, our Working at Height Safety Pack and Manual Handling Assessment Pack are £9.99 each as editable Word files. Or build your RAMS online: free preview, £9.99 for the editable Word file.

Useful HSE guidance: HSE: working at height · HSE: electrical safety.